PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ATHENA A BUILDING AND B BUILDINGMahaRERA P52100004030

by M/S KARAN VENKATESHWARA ASSOCIATES

SURVEY NO. 59/1,59/2,59/3, 411014

Oct 2021
Possession
100%
Built
4
Complaints
0
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Apr 2019, now proposed Oct 2021 per the RERA filing.

Official RERA facts

Registration
P52100004030
Status
Ongoing
Stage
Certificate Signed
Possession
October 2021originally April 2019
Construction
100% complete
Units sold
0 of 0

RERA complaint record4 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
12

Buyer community

Connect with other buyers and owners of ATHENA A BUILDING AND B BUILDING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ATHENA A BUILDING AND B BUILDING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.