Under construction

Eves Garden Phase V

by Sancheti Properties

34, Mundhwa, 411036

Jun 2019
Possession
50%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 50%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2019 per the RERA filing.

Official RERA facts

Registration
P52100004610
Status
Ongoing
Stage
Certificate Signed
Possession
June 2019
Construction
50% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths75%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of Eves Garden Phase V โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Eves Garden Phase V. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.