Under construction

PRERANA

by BPN ASSOCIATES

CTS NO 1376 TO1394, Pune (M Corp.), 411030

Jun 2019
Possession
52.7%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 52.7%.

Official RERA facts

Registration
P52100004966
Status
Ongoing
Stage
Certificate Signed
Possession
June 2019
Construction
52.7% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains90%
Water conservation /Rain water harvesting20%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
7

Buyer community

Connect with other buyers and owners of PRERANA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PRERANA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.