PropPin
All RERA projects
🏗️
Under construction

INDRAPRASTHA

MahaRERA P52100007400High risk

by OMKAR DEVELOPERS

GAT NO 698/2/3, GAT NO 698/2/3, 412220

Official record
Feb 2021
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Aug 2019, now proposed Feb 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Feb 2021) has passed with construction at 81.8%.

Promoter

Builder profile

Builder
OMKAR DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100007400
Status
Ongoing
Stage
Certificate Signed
Possession
February 2021originally August 2019
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Planting50%
Water conservation /Rain water harvesting25%
Energy managemcntnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of INDRAPRASTHA — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching INDRAPRASTHA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.