Under construction

Vtp Cygnus- Nation R1-Tower 8

by Ashdan Developers Private Limited

Gat Nos 155/156/157/158, Manjri, 412307

Jul 2024
Possession
90.9%
Built
23
Complaints
0
Units
High risk
  • 23 RERA complaints. 23 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jul 2024) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100007722
Status
Ongoing
Stage
Certificate Signed
Possession
July 2024originally July 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record23 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Planting80%
Street Lighting90%
Community Buildings80%
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposal90%
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station80%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
24
Architect
VK A ARCHITECTURE

Buyer community

Connect with other buyers and owners of Vtp Cygnus- Nation R1-Tower 8 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vtp Cygnus- Nation R1-Tower 8. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.