All RERA projects
๐๏ธ
Jun 2023
Possession
79.8%
Built
2
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 79.8%.
- Promised amenities not started. Swimming Pool, Landscaped Garden are at 0% build with possession due Jun 2023 per the RERA filing.
Official RERA facts
- Registration
- P52100007943
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2023originally June 2022
- Construction
- 79.8% complete
- Units sold
- 0 of 0
RERA complaint record2 records
- ComplaintCC1260380619 Jun 2026POOJA VIJAYKUMAR SURYAWANSHI vs NNP BUILDCON PVT. LTD
- ComplaintCC00500000015732611 Jul 2022Kartik Shah vs NNP Buildcon Pvt LtdOrder of Kartik Shah (2).pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths90%
Internal Roads & Footpathsnot started
Internal Roads & Footpaths90%
Internal Roads & Footpaths90%
Internal Roads & Footpaths25%
Water Supplynot started
Water Supplydone
Water Supply40%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drainsnot started
Storm Water Drainsnot started
Storm Water Drains35%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Planting80%
Landscaping & Tree Planting80%
Street Lightingnot started
Street Lightingnot started
Street Lightingnot started
Community Buildings65%
Community Buildings10%
Community Buildings65%
Treatment And Disposal Of Sewage And Sullage Water70%
Treatment And Disposal Of Sewage And Sullage Water60%
Treatment And Disposal Of Sewage And Sullage Water15%
Treatment And Disposal Of Sewage And Sullage Water70%
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposal15%
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposal15%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvesting50%
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Energy managemcntnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirements35%
Electrical meter room, sub-station, receiving stationnot started
Electrical meter room, sub-station, receiving station40%
Electrical meter room, sub-station, receiving station75%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Open Parkingnot started
Open Parkingnot started
Swimming Poolnot started
Loungenot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 28
Buyer community
Connect with other buyers and owners of VTP Alpine โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VTP Alpine. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.