Under construction

premia B-1 Phase II

by C.D. Developers

Survey No. 34/35 Village Narhe Taluka Haveli District Pune, NARHE, 411041

Oct 2018
Possession
43.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Oct 2018) has passed with construction at 43.6%.

Official RERA facts

Registration
P52100008990
Status
Ongoing
Stage
Certificate Signed
Possession
October 2018
Construction
43.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains50%
Landscaping & Tree Planting50%
Street Lightingnot started
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting30%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station70%

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of premia B-1 Phase II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching premia B-1 Phase II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.