Under construction

Aura Sai Krishnangan-Building A

by Bhagvati Infra

Gat No 420, 423 and 424 and CTS No 99 and 98, Koregaon Bhima (CT), 412216

Dec 2027
Possession
81.4%
Built
0
Complaints
55
Units
High risk
  • Possession delayed ~9 yrs. Originally promised Jan 2019, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100009487
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally January 2019
Construction
81.4% complete
Units sold
21 of 55

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains95%
Landscaping & Tree Planting95%
Street Lighting95%
Treatment And Disposal Of Sewage And Sullage Water95%
Solid Waste Management And Disposal95%
Water conservation /Rain water harvestingnot started
Energy managemcnt95%
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving station95%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
5
Unit mix
55 res ยท 0 comm
Architect
VINOD KHANZODE

Buyer community

Connect with other buyers and owners of Aura Sai Krishnangan-Building A โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aura Sai Krishnangan-Building A. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.