All RERA projects
๐๏ธ
Under construction
Sai Tirupati Greens Phase- I
Survey Number 131/1/1A/2, 131/1/1A/1/2, 131/2, Wadmukhwadi, 412105
Dec 2019
Possession
81.8%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 81.8%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2019 per the RERA filing.
Official RERA facts
- Registration
- P52100010061
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2019
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00500000005396421 Jan 2020Association of Allottees of Sai Tirupati Greens Scheme through Mr. Dnyaneshwar Bichewar vs Sai Tirupati Properties through partner Mr. Suresh V. PatilScan Order CC005-53964 dated 14-06-2022.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 13
Buyer community
Connect with other buyers and owners of Sai Tirupati Greens Phase- I โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Sai Tirupati Greens Phase- I. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.