Spine City Residency Building CMahaRERA P52100010634

by Spine Developers

Survey No 3 Kharabwadi, Kharabwadi, 410501

Aug 2022
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Feb 2021, now proposed Aug 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Aug 2022) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100010634
Status
Ongoing
Stage
Certificate Signed
Possession
August 2022originally February 2021
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Planting80%
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcnt20%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station20%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of Spine City Residency Building C โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Spine City Residency Building C. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.