ALANKAPURIMahaRERA P52100010797

by LAIGUDE DEVELOPERS

PLOT NO 33/2/1, wadgaon, 411041

Aug 2023
Possession
67.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Aug 2023) has passed with construction at 67.5%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Aug 2023 per the RERA filing.
Andheri WestUpper-mid

Entertainment-industry heartland — dense, lively, well connected.

Growth drivers:
Metro lines 1/2A, Lokhandwala–Versova redevelopment wave.
Who buys here:
Media professionals, first upgraders, rental investors.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P52100010797
Status
Ongoing
Stage
Certificate Signed
Possession
August 2023
Construction
67.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
10

Buyer community

Connect with other buyers and owners of ALANKAPURI — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching ALANKAPURI. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.