Under construction

Omega Paradise Wing L Phase 1

by Omega Promoters Private Ltd

S No 174 and 175 Part, wakad, 411057

Dec 2019
Possession
58.5%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 58.5%.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P52100011411
Status
Ongoing
Stage
Certificate Signed
Possession
December 2019originally December 2018
Construction
58.5% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting80%
Street Lighting80%
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting80%
Energy managemcntnot started
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Spacenot started
Open Parking80%
GYM50%

Building & registration

RERA registered
Aug 2017
Floors
12

Buyer community

Connect with other buyers and owners of Omega Paradise Wing L Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Omega Paradise Wing L Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.