Dec 2019
Possession
48.5%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 48.5%.
Official RERA facts
- Registration
- P52100011521
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2019originally December 2018
- Construction
- 48.5% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC0050000000958781 Sept 2021Nisarg Developers vs Sachin DattatrayShahane95878.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 5
Buyer community
Connect with other buyers and owners of RAJYOG RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching RAJYOG RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.