PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

NIVRUTTI HEIGHTS

by KALKI DEVELOPERS

GAT NO- 35,36, Pimpri Chinchawad (M Corp.), 412105

Sept 2020
Possession
90.9%
Built
8
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2020 per the RERA filing.

Official RERA facts

Registration
P52100011757
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record8 records

  • ComplaintCC1260077210 Feb 2026
    Vandana Sanjay Sul vs KALKI DEVELOPERS
  • ComplaintCC00500000008532718 Mar 2021
    Rajkumar Nivrutti Saste vs M/s Kalki Developers
    CC005000000085327 (1).pdf on MahaRERA
  • Misc. applicationCC00500000006465111 Oct 2020
    Vijay Arvind Dabhade vs Kalki Developers - Authorized Person - Mr. Dattatray Ramdas Dashpute
  • ComplaintCC00500000006465111 Oct 2020
    Vijay Arvind Dabhade vs Kalki Developers - Authorized Person - Mr. Dattatray Ramdas Dashpute
    64651.pdf on MahaRERA
  • ComplaintCC00500000005418626 Mar 2020
    NAVNATH ARVIND DABHADE vs M/S. KALKI DEVELOPERS
    CC005-54186 Order of Navnath Dabhade.pdf on MahaRERA
  • ComplaintCC0050000000228131 Apr 2019
    Rakeshkumar Rampyare Jaiswar and Pushpa Rakeshkumar Jaiswar vs M/s. Kalki Developers & Ors.
    22813.pdf on MahaRERA
  • Misc. applicationCC00500000001151917 May 2018
    Niranjan Dashpute vs RajKumar Nivrutti Saste, Sanjay Nivrutti Saste, Vijay Nivritti Saste
    11519 order final.pdf on MahaRERA
  • ComplaintCC00500000001151917 May 2018
    Niranjan Dashpute vs RajKumar Nivrutti Saste, Sanjay Nivrutti Saste, Vijay Nivritti Saste
    11519 order final.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements40%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of NIVRUTTI HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIVRUTTI HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.