Under construction

SANTIAGO SKYMONTMahaRERA P52100012533

by ASHA HERITAGE DEVELOPERS

SR NO 153 HISSA NO 2, -, 412105

Dec 2030
Possession
30.2%
Built
4
Complaints
142
Units
High risk
  • Possession delayed ~10 yrs. Originally promised Dec 2020, now proposed Dec 2030 per the RERA filing.

Official RERA facts

Registration
P52100012533
Status
Ongoing
Stage
Certificate Signed
Possession
December 2030originally December 2020
Construction
30.2% complete
Units sold
59 of 142

RERA complaint record4 records

Complaint data not yet synced for this project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2017
Floors
20 (sanctioned 16)
Unit mix
142 res ยท 0 comm
Architect
MAHINDRA THAKUR

Buyer community

Connect with other buyers and owners of SANTIAGO SKYMONT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SANTIAGO SKYMONT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.