SHINDE ASSOCIATESMahaRERA P52100012546
S. No. 42/3B/3,8,42/4/3,6,7,8,15,16,20,26,31,32,33,37.Mohammadwadi, Pune, 411060
Mar 2027
Possession
14.1%
Built
0
Complaints
43
Units
High risk
- Possession delayed ~4 yrs. Originally promised Nov 2022, now proposed Mar 2027 per the RERA filing.
- Behind schedule. Possession is due Mar 2027 but construction is only at 14.1%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100012546
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2027originally November 2022
- Construction
- 14.1% complete
- Units sold
- 0 of 43
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Sept 2017
- Floors
- 11
- Unit mix
- 43 res ยท 0 comm
- Architect
- Vilas Tarwadi
Buyer community
Connect with other buyers and owners of SHINDE ASSOCIATES โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHINDE ASSOCIATES. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.