Under construction

GAURAV PARK

by RENUKA CONSTRUCTIONS

PLOT NO 136 AND 137, TAPODHAM COLONY, 410507

Sept 2022
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2019, now proposed Sept 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2022 per the RERA filing.

Official RERA facts

Registration
P52100012750
Status
Ongoing
Stage
Certificate Signed
Possession
September 2022originally September 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply98%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone

Building & registration

RERA registered
Sept 2017
Floors
6

Buyer community

Connect with other buyers and owners of GAURAV PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GAURAV PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.