SHRI RENUKA ASSOCIATES VANSHRI MAMURDI PROJECT

by SHRI RENUKA ASSOCIATES

SR NO 13/1A/1 PART MAMURDI PUNE, NEAR MAVAL GATE HOTEL, 412101

Dec 2024
Possession
18.2%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Oct 2020, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 18.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.

Official RERA facts

Registration
P52100013840
Status
New
Stage
Certificate Signed
Possession
December 2024originally October 2020
Construction
18.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parking16%

Building & registration

RERA registered
Oct 2017
Floors
10

Buyer community

Connect with other buyers and owners of SHRI RENUKA ASSOCIATES VANSHRI MAMURDI PROJECT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHRI RENUKA ASSOCIATES VANSHRI MAMURDI PROJECT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.