PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Grande View 7 Phase III Building K

by Chirag Developers

6/4,5,6,7,8,6/12,13,14,15, AMBEGAON bk, 411046

Dec 2021
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2021 per the RERA filing.

Official RERA facts

Registration
P52100013947
Status
New
Stage
Certificate Signed
Possession
December 2021
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Space50%
Open Parking30%
Transformer Roomdone
Club House30%
Entrance Gate30%

Building & registration

RERA registered
Nov 2017
Floors
15

Buyer community

Connect with other buyers and owners of Grande View 7 Phase III Building K โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Grande View 7 Phase III Building K. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.