Dec 2023
Possession
87.1%
Built
0
Complaints
44
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2021, now proposed Dec 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 87.1%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2023 per the RERA filing.
Official RERA facts
- Registration
- P52100014266
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2023originally December 2021
- Construction
- 87.1% complete
- Units sold
- 40 of 44
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths80%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsdone
Landscaping & Tree Planting20%
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Nov 2017
- Floors
- 15
- Unit mix
- 44 res ยท 0 comm
- Architect
- MRS USHA RANGRAJAN
Buyer community
Connect with other buyers and owners of EXCEL CELESTIA RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching EXCEL CELESTIA RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.