PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ICONIA Phase III

by Kunal Sulakshan Associates

S. No. 10 1A, Mamurdi, Pimpri Chinchawad (M Corp.), 412101

Dec 2022
Possession
100%
Built
0
Complaints
0
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100014286
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
100% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains60%
Landscaping & Tree Planting75%
Street Lighting60%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Space50%
Open Parkingnot started

Building & registration

RERA registered
Nov 2017
Floors
13

Buyer community

Connect with other buyers and owners of ICONIA Phase III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ICONIA Phase III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.