Under construction

LOTUS LAXMI 3

by SURYA PROPERTIES

SURVEY NO. 40/1/4/4A, RAVET, 412101

Sept 2020
Possession
85.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 85.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2020 per the RERA filing.

Official RERA facts

Registration
P52100015530
Status
New
Stage
Certificate Signed
Possession
September 2020
Construction
85.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station80%

Building & registration

RERA registered
Mar 2018
Floors
8

Buyer community

Connect with other buyers and owners of LOTUS LAXMI 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LOTUS LAXMI 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.