Under construction

Mayuri Infinity

by MAYURI LANDMARKSLLP

27 4, TATA inora park, 411028

Apr 2024
Possession
66.7%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Apr 2021, now proposed Apr 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2024) has passed with construction at 66.7%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Apr 2024 per the RERA filing.

Official RERA facts

Registration
P52100015703
Status
New
Stage
Certificate Signed
Possession
April 2024originally April 2021
Construction
66.7% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Street Lighting50%
Community Buildingsnot started
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Space50%
Open Parking50%

Building & registration

RERA registered
Mar 2018
Floors
15

Buyer community

Connect with other buyers and owners of Mayuri Infinity โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Mayuri Infinity. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.