All RERA projects
๐๏ธ
Under construction
DNYANESHWARI COMPLEXMahaRERA P52100016255
by Shree Raghunath Maharaj Developers
GAT NO 116 3 P, CHOVISWADI, 412105
Dec 2019
Possession
47.7%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 47.7%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2019 per the RERA filing.
Official RERA facts
- Registration
- P52100016255
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2019
- Construction
- 47.7% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Apr 2018
- Floors
- 5
Buyer community
Connect with other buyers and owners of DNYANESHWARI COMPLEX โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching DNYANESHWARI COMPLEX. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.