MANAS RESIDENCYMahaRERA P52100016431

by OORJITAA REALTORS

2619-1/A/1-PART AND 2619 -1/A/1-PART, aalephata, 412411

Dec 2026
Possession
78.6%
Built
0
Complaints
48
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100016431
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
78.6% complete
Units sold
17 of 48

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting85%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station25%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2018
Floors
5
Unit mix
48 res ยท 0 comm
Architect
TRIPTI GUPTA ARCHITECTS AND DESIGNERS

Buyer community

Connect with other buyers and owners of MANAS RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MANAS RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.