AVALON HEIGHTMahaRERA P52100016480

by AVALON PROPERTIES LLP

165/2/1, WAKAD, 411057

Mar 2022
Possession
53.6%
Built
0
Complaints
3
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 53.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52100016480
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
53.6% complete
Units sold
0 of 3

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2018
Floors
13

Buyer community

Connect with other buyers and owners of AVALON HEIGHT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AVALON HEIGHT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.