Under construction

ATLANTEMahaRERA P52100016663

by PYRAMID INFRAVENTURE LLP

56/2/1,56/2/2,56/2/3,56/2/4, Mulshi, 411033

Dec 2027
Possession
72.5%
Built
0
Complaints
0
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100016663
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
72.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains70%
Landscaping & Tree Planting80%
Street Lighting60%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting70%
Energy managemcnt70%
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacedone
Open Parking50%
SWIMMING POOLdone
PARTY LAWNdone
GYMdone
CLUB HOUSEdone
CHILDREN PLAY AREAdone
AMPHI THEATHERdone

Building & registration

RERA registered
Jun 2018
Floors
29

Buyer community

Connect with other buyers and owners of ATLANTE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ATLANTE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.