ANUJAI RESIDENCYMahaRERA P52100016816
Sr no 43/3B/3, Pimple nilakh, 411027
Mar 2019
Possession
63.6%
Built
0
Complaints
25
Units
High risk
- Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 63.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2019 per the RERA filing.
Official RERA facts
- Registration
- P52100016816
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2019
- Construction
- 63.6% complete
- Units sold
- 12 of 25
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains60%
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station60%
Building & registration
- RERA registered
- Jun 2018
- Floors
- 8
- Unit mix
- 22 res ยท 3 comm
- Architect
- Mr Vivek Girish Nagpurkar
Buyer community
Connect with other buyers and owners of ANUJAI RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ANUJAI RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.