PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ROSE CASTLEMahaRERA P52100016884

by Rose Crystal Developers

112, Near Panchsheel Club, Moshi, 412105

Sept 2025
Possession
88.9%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised May 2022, now proposed Sept 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 88.9%.

Official RERA facts

Registration
P52100016884
Status
New
Stage
Certificate Signed
Possession
September 2025originally May 2022
Construction
88.9% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC1250053716 Feb 2025
    Shridarshan Gopichand Badgujar vs Rose Crystal Developers

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains90%
Landscaping & Tree Planting90%
Street Lighting90%
Community Buildings95%
Water conservation /Rain water harvesting90%
Energy managemcntnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2018
Floors
12

Buyer community

Connect with other buyers and owners of ROSE CASTLE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ROSE CASTLE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.