Under construction

SKY PAVILION Phase IIMahaRERA P52100018243

by SKP Corp Private Limited

Sr No 62/2/2 Part and 60/3 Undri Pune, Haveli, 411060

Dec 2026
Possession
96.5%
Built
0
Complaints
53
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100018243
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
96.5% complete
Units sold
22 of 53

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsdone
Landscaping & Tree Planting85%
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Oct 2018
Floors
5
Unit mix
0 res ยท 53 comm
Architect
Manoj Tatooskar

Buyer community

Connect with other buyers and owners of SKY PAVILION Phase II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SKY PAVILION Phase II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.