Under construction

Akshay AnantamMahaRERA P52100018878

by Sneh Constructions

Survey No 168/2 Part and 4 Part, Near Datta Mandir, 411057

Mar 2028
Possession
78.9%
Built
13
Complaints
194
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Aug 2023, now proposed Mar 2028 per the RERA filing.
  • 13 RERA complaints. 13 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P52100018878
Status
New
Stage
Certificate Signed
Possession
March 2028originally August 2023
Construction
78.9% complete
Units sold
159 of 194

RERA complaint record13 records

  • ComplaintCC126043019 Jul 2026
    Sagar Sanjay Malpure vs Sneh Constructions
  • ComplaintCC1260403429 Jun 2026
    Mandar Arvind Bonde vs Sneh Constructions
  • ComplaintCC1260367013 Jun 2026
    Yogesh Dattatray Sorte vs Sneh Constructions
  • ComplaintCC1260158322 Mar 2026
    Farida Riyaj Jamadar vs Sneh Constructions
  • ComplaintCC1260142114 Mar 2026
    Abhijit Bhagawat Sinkar vs Sneh Constructions
  • ComplaintCC1260142014 Mar 2026
    Gyanesh Agarwal vs Sneh Constructions
  • ComplaintCC1260141914 Mar 2026
    Shashikant Shrihari Karande vs Sneh Constructions
  • ComplaintCC1260143414 Mar 2026
    Vinayak Ananda Bharmal vs Sneh Constructions
  • ComplaintCC126012809 Mar 2026
    Amit Dilipkumar Kochar vs Sneh Constructions
  • ComplaintCC125031879 Sept 2025
    POOJA CHANDRAKANT GURIKAR vs Sneh Constructions
    Order of Pooja Gurikar (1).pdf on MahaRERA
  • ComplaintCC00500000047145015 Aug 2024
    Vinayak Ananda Bharmal vs Nitin Bhansali
    Order of Vinayak Bharmal.pdf on MahaRERA
  • ComplaintCC0050000003105494 Mar 2024
    Rajendra Hilal Patil vs M/S Sneh Constructions
    Common Order of Sneh Constructions-2 complaints (3).pdf on MahaRERA
  • ComplaintCC0050000003105514 Mar 2024
    Gunjan Rajendra Patil vs M/S Sneh Constructions
    Common Order of Sneh Constructions-2 complaints (3).pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supply99%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains50%
Landscaping & Tree Planting15%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting60%
Energy managemcnt15%
Fire protection and fire safety requirements40%
Electrical meter room, sub-station, receiving station95%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Dec 2018
Floors
13
Unit mix
193 res ยท 1 comm
Architect
Vastushilp

Buyer community

Connect with other buyers and owners of Akshay Anantam โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Akshay Anantam. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.