PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

YashONE Hinjawadi - Phase 1MahaRERA P52100019468

by Vilas Javdekar Eco Shelters Private Limited

S.no.29/1 P,29/2 P,31,32 P,43/5, 43/6 P, Hinjawadi, 411057

Dec 2023
Possession
99.2%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 99.2%.

Official RERA facts

Registration
P52100019468
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
99.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains69%
Landscaping & Tree Planting71%
Street Lighting10%
Community Buildings99%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting70%
Energy managemcnt80%
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Space76%
Open Parking76%

Building & registration

RERA registered
Feb 2019
Floors
24

Buyer community

Connect with other buyers and owners of YashONE Hinjawadi - Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching YashONE Hinjawadi - Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.