Under construction

Siyona Phase - IIMahaRERA P52100020135

by PETHKAR PROJECTS

S.NO 47 PART, 48 PART, 50 PART, Mulshi, 411033

Mar 2029
Possession
60.9%
Built
0
Complaints
376
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2026, now proposed Mar 2029 per the RERA filing.

Official RERA facts

Registration
P52100020135
Status
New
Stage
Certificate Signed
Possession
March 2029originally December 2026
Construction
60.9% complete
Units sold
184 of 376

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lighting50%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started
Open Parking50%

Building & registration

RERA registered
Mar 2019
Floors
26
Unit mix
376 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Siyona Phase - II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Siyona Phase - II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.