PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Ganga Fernhill phase 02MahaRERA P52100022705

by MEENAMANI GANGA BUILDERS LLP

23 part, Undri, 411060

Dec 2026
Possession
78.4%
Built
3
Complaints
186
Units
Caution
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100022705
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
78.4% complete
Units sold
186 of 186

RERA complaint record3 records

  • ComplaintCC126027119 May 2026
    Nivrutti Venkat Nadagude vs MEENAMANI GANGA BUILDERS LLP
  • ComplaintCC126026517 May 2026
    Fatima Murtuza Pota vs MEENAMANI GANGA BUILDERS LLP
  • ComplaintCC126005491 Feb 2026
    Shubham Ashok Kharche vs MEENAMANI GANGA BUILDERS LLP

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths30%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting30%
Street Lighting10%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2019
Floors
14
Unit mix
186 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Ganga Fernhill phase 02 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.