PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ELINA LIVING PHASE III

by Ramkrishna Cine Exhibitors

S No43 part, 44 and 46 part, KONDHWA, 411060

Jun 2024
Possession
100%
Built
1
Complaints
0
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2024 per the RERA filing.

Official RERA facts

Registration
P52100023154
Status
New
Stage
Certificate Signed
Possession
June 2024
Construction
100% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Dec 2019
Floors
24

Buyer community

Connect with other buyers and owners of ELINA LIVING PHASE III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ELINA LIVING PHASE III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.