Under construction

VTP Cygnus BuildingT12 and CommercialMahaRERA P52100023473

by ARHUM ERECTORS PRIVATE LIMITED

sno124 125 126 to 132 140 to 145 160 to, Manjari, 412307

Jun 2025
Possession
84.6%
Built
3
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 84.6%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2025 per the RERA filing.

Official RERA facts

Registration
P52100023473
Status
New
Stage
Certificate Signed
Possession
June 2025
Construction
84.6% complete
Units sold
0 of 0

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains95%
Landscaping & Tree Plantingnot started
Street Lighting30%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water95%
Solid Waste Management And Disposal95%
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station95%

Building & registration

RERA registered
Dec 2019
Floors
29
Architect
vk arch

Buyer community

Connect with other buyers and owners of VTP Cygnus BuildingT12 and Commercial โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VTP Cygnus BuildingT12 and Commercial. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.