N B OPAL PHASE -IMahaRERA P52100023516

by Nanasaheb Bhintade Spacess Pvt. Ltd.

3/1/4/1A/1B/1C/1D, Near Podar international school, 411046

Dec 2023
Possession
98.2%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 98.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P52100023516
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
98.2% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space20%

Building & registration

RERA registered
Dec 2019
Floors
22

Buyer community

Connect with other buyers and owners of N B OPAL PHASE -I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching N B OPAL PHASE -I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.