Under construction

PARSHWA

MahaRERA P52100024982Caution

by Kotibhaskar Infrastructures &Developers Pvt.Ltd.

Plot No 45 Survey No 129 CTS No 766 Shree Durga Co Op Housing soc, Kothrud, 411038

Official record
May 2023
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (May 2023) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
Kotibhaskar Infrastructures &Developers Pvt.Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100024982
Status
New
Stage
Certificate Signed
Possession
May 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Mar 2020
Floors
9

Buyer community

Connect with other buyers and owners of PARSHWA — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching PARSHWA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.