GANGA AMBER PH II
by SHRI SIDDHIVINAYAK DEVELOPERS
59 PART , 60 3, Mulshi, 411033
- Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Jun 2027 per the RERA filing.
- 23 RERA complaints. 23 complaint records are disclosed against this project on MahaRERA.
- Behind schedule. Possession is due Jun 2027 but construction is only at 43%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100026055
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027originally June 2025
- Construction
- 43% complete
- Units sold
- 90 of 206
RERA complaint record23 records
- ComplaintCC1260448118 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Mayur Umesh Phadke
- ComplaintCC1260448618 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Devendra yashwant Palav
- ComplaintCC1260448318 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Bhagwan Vishwanath Shrirame
- ComplaintCC1260448918 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Sonal Sagar Lakade
- ComplaintCC1260449318 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Sangeeta Sameer Bhole
- ComplaintCC1260447218 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Sunil Wamanrao Kadam
- ComplaintCC1260447518 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Vaibhav Ganesh Bhole
- ComplaintCC1260446017 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Shrusti Prashant Deshmukh
- ComplaintCC1260446117 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Neha Ganesh Bhole
- ComplaintCC1260446217 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Lalit Ravindra Amrutkar
- ComplaintCC1260445917 Jul 2026SHRI SIDDHIVINAYAK DEVELOPERS vs Mr Abhishek Chandrakant Yadav
- ComplaintCC1250350030 Sept 2025Vaibhav ganesh Bhole vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC1250347429 Sept 2025Neha Ganesh Bhole vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC1250347529 Sept 2025mayur umesh phadke vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC125021992 Jul 2025SONAL SAGAR LAKADE vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC125011274 Apr 2025sangeeta Sameer Bhole vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC1250103127 Mar 2025Mayur Lalchand Jiwatramani vs SHRI SIDDHIVINAYAK DEVELOPERSCC12501031.pdf on MahaRERA
- ComplaintCC125007171 Mar 2025Sunil Wamanrao Kadam vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC1250070428 Feb 2025Abhishek CHANDRAKANT Yadav vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC1250070128 Feb 2025Lalit Ravindra Amrutkar vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC1250070628 Feb 2025Devendra Yashwant Palav vs Anuj Goel
- ComplaintCC1250070528 Feb 2025BHAGAWAN VISHWANATH SHRIRAME vs SHRI SIDDHIVINAYAK DEVELOPERS
- ComplaintCC1250065524 Feb 2025Shrushti Prashant Deshmukh vs SHRI SIDDHIVINAYAK DEVELOPERS
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2020
- Floors
- 14
- Unit mix
- 206 res · 0 comm
Buyer community
Connect with other buyers and owners of GANGA AMBER PH II — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching GANGA AMBER PH II. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.