PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Green County Phase II Wing-BMahaRERA P52100026716

by Anand Developers

S. No. 171/6C, 171/7/1, Fursungi, 412307

Jun 2025
Possession
86.1%
Built
0
Complaints
222
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 86.1%.

Official RERA facts

Registration
P52100026716
Status
New
Stage
Certificate Signed
Possession
June 2025
Construction
86.1% complete
Units sold
160 of 222

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting95%
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcnt95%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station95%
Aggregate area of recreational Open Space85%
Open Parkingdone

Building & registration

RERA registered
Oct 2020
Floors
17
Unit mix
222 res ยท 0 comm
Architect
A Design Studio

Buyer community

Connect with other buyers and owners of Green County Phase II Wing-B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Green County Phase II Wing-B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.