PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

THE BUSINESS GATEMahaRERA P52100029275

by Kesar Vasudev Properties

GAT NO. 32, MOSHI, MOSHI, PUNE, 412105

Oct 2026
Possession
81.8%
Built
1
Complaints
280
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2024, now proposed Oct 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Oct 2026 per the RERA filing.

Official RERA facts

Registration
P52100029275
Status
New
Stage
Certificate Signed
Possession
October 2026originally March 2024
Construction
81.8% complete
Units sold
117 of 280

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsnot started
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2021
Floors
9
Unit mix
0 res ยท 280 comm
Architect
S S WALI AND ASSOCIATES

Buyer community

Connect with other buyers and owners of THE BUSINESS GATE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE BUSINESS GATE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.