Under construction

BLUE BELLS PHASE 2MahaRERA P52100031327

by KAVITA DEVRAM WALHEKAR

PAP-R-93, PAP-R-94, RAJIV GANDHI INFOTECH PARK, PHASE - II, MAAN, HINJAWADI, 411057

Dec 2023
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2022, now proposed Dec 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 81.8%.

Official RERA facts

Registration
P52100031327
Status
New
Stage
Certificate Signed
Possession
December 2023originally March 2022
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Oct 2021
Floors
4

Buyer community

Connect with other buyers and owners of BLUE BELLS PHASE 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BLUE BELLS PHASE 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.