Wonder CountyMahaRERA P52100032072
228 Part, 230 Part, 231 Part and 235 Part, Near Saswad Bhopdev Road, 412301
Dec 2028
Possession
โ
Built
2
Complaints
183
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2024, now proposed Dec 2028 per the RERA filing.
Official RERA facts
- Registration
- P52100032072
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028originally December 2024
- Construction
- โ
- Units sold
- 141 of 183
RERA complaint record2 records
- ComplaintCC126011643 Mar 2026SANDEEP ASHOK JADHAV vs Maple Promoters and Builders
- ComplaintCC1260110228 Feb 2026Surjo Samiran Banerjee vs Maple Promoters and Builders
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths90%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsnot started
Landscaping & Tree Planting75%
Street Lighting90%
Community Buildingsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Dec 2021
Buyer community
Connect with other buyers and owners of Wonder County โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Wonder County. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.