Under construction

Basil MondaleMahaRERA P52100033136

by velx constructions llp

survey no 32 hissa no 1A Hissa 1B, Keshavnagar, 411036

Dec 2025
Possession
84.2%
Built
1
Complaints
542
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 84.2%.

Official RERA facts

Registration
P52100033136
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
84.2% complete
Units sold
534 of 542

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains75%
Landscaping & Tree Planting50%
Street Lighting65%
Community Buildings45%
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting55%
Energy managemcntnot started
Fire protection and fire safety requirements65%
Electrical meter room, sub-station, receiving station65%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2022
Floors
16
Unit mix
542 res ยท 0 comm
Architect
R S ASSOCIATES

Buyer community

Connect with other buyers and owners of Basil Mondale โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Basil Mondale. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.