PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Mihir Amara Phase 1

by Mihir Synthetics

S. No. 153/1/A Part, 153/20, 21, 22, 24, 27, 31, 33, 34, 35, Mulshi, 411057

โ€”
Possession
โ€”
Built
8
Complaints
โ€”
Units
Caution
  • 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P52100033531
Status
โ€”
Stage
โ€”
Possession
โ€”
Construction
โ€”
Units sold
โ€”

RERA complaint record8 records

  • ComplaintCC1260434111 Jul 2026
    Prashant S KULKARNI vs Mihir Synthetics
  • ComplaintCC1260327931 May 2026
    saket kumar gupta vs Mihir Synthetics
  • ComplaintCC1260307524 May 2026
    Kumar Chhajed vs Mihir Synthetics
  • ComplaintCC1260301921 May 2026
    Mihir Synthetics vs Sharwari Amod Mhetar
  • ComplaintCC1260236722 Apr 2026
    Amol Patil vs Mihir Synthetics
  • ComplaintCC1260235921 Apr 2026
    Pratik Prakash Thakare vs Mihir Synthetics
  • ComplaintCC1260235821 Apr 2026
    Ganesh Mahadev Gite vs Mihir Synthetics
  • ComplaintCC1260187630 Mar 2026
    Ashish Jaiswal vs Mihir Synthetics

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains90%
Landscaping & Tree Planting50%
Street Lighting25%
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Water80%
Water conservation /Rain water harvesting80%
Energy managemcnt70%
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Space50%
Open Parkingnot started

Building & registration

RERA registered
Feb 2022
Floors
33
Unit mix
312 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Mihir Amara Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Mihir Amara Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.