Shiva Residency
69/10/1/31, Near Yamai Mandir Dighi, 411015
- Possession date passed. The proposed possession date (May 2025) has passed with construction at 89.1%.
Official RERA facts
- Registration
- P52100035062
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2025originally October 2024
- Construction
- 89.1% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
DEEPALI SHIVAJI RAJGURAV, Balkrishna Ramchandra Gurav
Possession extension history
- EXT52100025167Revised to May 2025
We would like to provide detailed reasons and clarification regarding the delay in the project and the necessity for an extension. Reason for Delay: The delay is primarily due to a shortage of funds, which temporarily impacted the progress of the project. Pending Work: The only remaining tasks are the installation of the lift and completion certificate (CC) processing. Work Completed: 95% of the project has been successfully completed. Balance Work: 5% of the project remains to be completed. The remaining work is planned to be completed within the proposed extension period, with the revised deadline set for 30/05/2024.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- May 2022
- Floors
- 6
- Plot / CTS / survey no.
- 69/10/1/31
- Planning authority
- PCMC
- Approved layout land
- 286.81 sq.m
- Land for this registration
- 286.81 sq.m
- Permissible built-up area
- 502.27 sq.m
- Promoter contact
- DEEPALI SHIVAJI RAJGURAV
- Registered office
- Sai Vihar Apartments
- North
- Road
- South
- S No 69-11
- East
- Plot of Mr Shinde
- West
- Plot of Mr Phadtare
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- UNION BANK OF INDIA โ 148160IFSC UBIN0558397C Building Plot No 14,Sai Vihar Complex, Talegaon Chakan Road, Talegaon Station 410507
Commencement Certificate documents
- Commencement Letter.pdf
Buyer community
Connect with other buyers and owners of Shiva Residency โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Shiva Residency. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.