Under construction

AYODHYA CAPITALMahaRERA P52100046657

by AYODHYA CAPITAL

14/9(P), Haveli, 411033

Dec 2027
Possession
40.5%
Built
0
Complaints
79
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Jun 2025, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100046657
Status
New
Stage
Certificate Signed
Possession
December 2027originally June 2025
Construction
40.5% complete
Units sold
0 of 79

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2022
Floors
14
Unit mix
0 res ยท 79 comm
Architect
KEDAR KAMAT

Buyer community

Connect with other buyers and owners of AYODHYA CAPITAL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AYODHYA CAPITAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.