Under construction

BUSINESS HUBMahaRERA P52100047555

by Rajendra Venkat Reddy

SR NO 140-1, BANER, 411045

Jul 2028
Possession
81.8%
Built
0
Complaints
2
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jul 2025, now proposed Jul 2028 per the RERA filing.

Official RERA facts

Registration
P52100047555
Status
New
Stage
Certificate Signed
Possession
July 2028originally July 2025
Construction
81.8% complete
Units sold
2 of 2

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Nov 2022
Floors
8
Unit mix
0 res ยท 2 comm
Architect
Vilas Tarawadi

Buyer community

Connect with other buyers and owners of BUSINESS HUB โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BUSINESS HUB. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.