Under construction

AG BUSINESS PARKMahaRERA P52100047954

by A G Constructions

279/1 279/2 279/2/1 279/2/2 279/2/3 280/1 280/2 280/3, Baner, 411005

Jan 2028
Possession
42.7%
Built
0
Complaints
15
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Jan 2026, now proposed Jan 2028 per the RERA filing.

Official RERA facts

Registration
P52100047954
Status
New
Stage
Certificate Signed
Possession
January 2028originally January 2026
Construction
42.7% complete
Units sold
0 of 15

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Dec 2022
Floors
21
Unit mix
0 res ยท 15 comm

Buyer community

Connect with other buyers and owners of AG BUSINESS PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AG BUSINESS PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.