ABHANG

MahaRERA P52100049415High risk

by SUREKHA VISHNU KUMBHAR

GAT NO -141,Plot NO -4, KANCHAN NAGAR, 413102

Official record
Oct 2025
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Oct 2025) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2025 per the RERA filing.

Promoter

Builder profile

Builder
SUREKHA VISHNU KUMBHAR

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100049415
Status
New
Stage
Certificate Signed
Possession
October 2025
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Feb 2023
Floors
6

Buyer community

Connect with other buyers and owners of ABHANG — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching ABHANG. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.